One week of float remains before the 18 Sep cutover.
Cutover program / weekly status
Cutover holds at three weeks out, with rollback tooling the pacing risk.
Objective Migrate every customer account to the new ledger with zero billing discrepancies and no unplanned downtime during business hours.
- Sponsor
- Diane Osei
- Program lead
- Priya Nandan
- Next review
- 8 Sep / 10:00
Program completion
68% complete
Three weeks to the go-live window
$412k of the $475k program budget is committed.
Multi-currency display moved to phase two this week.
Down eight points while rollback tooling is blocked.
Workstreams
Milestones
-
Migration dry-run / cohorts 1–3
Complete with zero reconciliation errors.
-
Rollback tooling sign-off
Slipped from 25 Aug pending infrastructure access.
-
Go / no-go review
Sponsor review of the four release gates.
-
Cutover weekend
Ledger migration executes Friday overnight.
Risks
Rollback tooling cannot be validated without production-scale data.
Escalate the replica request to the infrastructure director by Friday.Sandbox instability could mask a real payment webhook issue.
Run the same contract suite against vendor staging in parallel.Decisions needed
Move multi-currency display to phase two to protect the cutover date.
- Owner
- Diane Osei
- Due
- 8 Sep
Prioritize the read replica request over lower-risk infrastructure work.
- Owner
- Diane Osei
- Due
- 4 Sep