Beacon / Program office

Status report 18

Cutover program / weekly status

Cutover holds at three weeks out, with rollback tooling the pacing risk.

Objective Migrate every customer account to the new ledger with zero billing discrepancies and no unplanned downtime during business hours.

Sponsor
Diane Osei
Program lead
Priya Nandan
Next review
8 Sep / 10:00

Program completion

68% complete

Three weeks to the go-live window

Timeline 72%

One week of float remains before the 18 Sep cutover.

Budget 87%

$412k of the $475k program budget is committed.

Scope 90%

Multi-currency display moved to phase two this week.

Confidence 65%

Down eight points while rollback tooling is blocked.

01

Workstreams

Workstream Owner Status This week
Data migration Priya Nandan On track Dry-run four of five completed with zero reconciliation errors.
Integration testing Marcus Webb At risk Payment-gateway contract retest scheduled for Thursday.
Rollback tooling Sam Okafor Blocked Production-scale read replica access remains outstanding.
Customer communications Elena Cho On track Cutover notice cleared legal review and sends on 10 Sep.
02

Milestones

  1. Migration dry-run / cohorts 1–3

    Complete with zero reconciliation errors.

  2. Rollback tooling sign-off

    Slipped from 25 Aug pending infrastructure access.

  3. Go / no-go review

    Sponsor review of the four release gates.

  4. Cutover weekend

    Ledger migration executes Friday overnight.

03

Risks

HighSam Okafor

Rollback tooling cannot be validated without production-scale data.

Escalate the replica request to the infrastructure director by Friday.
MediumMarcus Webb

Sandbox instability could mask a real payment webhook issue.

Run the same contract suite against vendor staging in parallel.
04

Decisions needed

Move multi-currency display to phase two to protect the cutover date.

Owner
Diane Osei
Due
8 Sep

Prioritize the read replica request over lower-risk infrastructure work.

Owner
Diane Osei
Due
4 Sep
05

Next seven days

  1. Tue

    Escalate rollback access to the infrastructure director.

    Sam Okafor
  2. Wed

    Run payment-gateway tests against vendor staging.

    Marcus Webb
  3. Thu

    Complete the final migration dry-run cohort.

    Priya Nandan
  4. Mon

    Send the first regional customer notice.

    Elena Cho